KoloDC: Planned maintenance gensets powerfeed A NL2 (Meppel)

Onderstaand bericht ontvingen wij van onze leverancier:

-- We would like to inform you about scheduled maintenance on powerfeed A backup generators at our NL2 data center in Meppel. This planned work is part of our regular upkeep and is not expected to impact the availability of your services.

Maintenance Details:

Schedule:
From 24 November to 26 November 2025
Daily between 09:00 and approximately 17:00 CET (Amsterdam time)
Location: NL2, Meppel, The Netherlands
Scope: A-Feed backup power generators maintenance
Service Impact: Low
Outage: None anticipated

--

KoloDC: Planned Maintenance – Electrical inspection at NL1 Dronten (last part)

Onderstaand bericht ontvingen wij van KoloDC:

We would like to inform you about scheduled maintenance on the electrical infrastructure at our NL1 data center in Dronten. This planned work is part of our regular upkeep and is not expected to impact the availability of your services.

Maintenance Details:

Schedule: 8 December 2025 09:00 – 17:00 CET
Location: NL1, room 1,2 and 4, Dronten, The Netherlands
Scope: Electrical sub panels C-feed (room 1,2 and 4) inspection (visual + thermographical)
Service Impact: Low
Outage: None anticipated

Past Incidents

Monday 10th November 2025

KoloDC: Yearly electrical inspection Dronten NL1, scheduled 1 week ago

Onderstaand bericht ontvingen wij van KoloDC:

We would like to inform you about scheduled maintenance (inspection) on the electrical boards and lighting systems at our NL1 data center in Dronten. This planned work is part of our regular upkeep and is not expected to impact the availability of your services.

Maintenance Details:

Schedule:
From 10 November 2025 untill 14 november 2025
Daily between 09:00 and approximately 17:00 CET
Location: NL1, Dronten, The Netherlands
Scope: inspections of MDB, SDB boards and lighting systems
Service Impact: Low
Outage: None anticipated

Friday 7th November 2025

KoloDC: Planned Maintenance – UPS System at NL2 Meppel, scheduled 2 weeks ago

Onderstaand bericht ontvingen wij van KoloDC:

We would like to inform you about scheduled maintenance on our UPS system at our NL2 data center in Meppel. This planned work is part of our regular upkeep and is not expected to impact the availability of your services.

Maintenance Details:

Schedule:
From 7 November 2025 to 7 November 2025
Between 09:00 and approximately 17:00 CET
Location: NL2, Meppel, The Netherlands
Scope: UPS system maintenance
Service Impact: Low
Outage: None anticipated

Thursday 30th October 2025

No incidents reported

Wednesday 29th October 2025

No incidents reported

Tuesday 28th October 2025

No incidents reported

Monday 27th October 2025

No incidents reported

Sunday 26th October 2025

DC1: Preventief ATS vervangen, scheduled 4 weeks ago

Vanuit onze monitoring hebben wij de afgelopen dagen enkele meldingen ontvangen van één van onze ATS-switches (Automatic Transfer Switch) in DC1 (Dronten).

Hoewel de switch momenteel nog naar behoren functioneert, zullen wij deze preventief vervangen om ongeplande storingen in de toekomst te voorkomen. Tijdens deze werkzaamheden zal er een korte onderbreking plaatsvinden voor apparatuur met een enkele PSU in rack 1.1.9. Het betreft slechts een klein aantal systemen, waardoor de impact minimaal zal zijn.

De vervanging staat gepland voor de late avond, om eventuele impact verder te beperken.