dinsdag 27th oktober 2020

Serverius: Dark fiber onderhoud van leverancier Relined, gepland 3 jaar geleden

Onderstaand bericht ontvingen wij van Serverius:

You are receiving this message as advance notice because our dark fiber suppliers “Relined” will do a Service-Affecting maintenances PA-843001.

Location: SDC2, Meppel, NL, Service Type: Dark fiber

Start: 2020-11-07 00:00:00 CET, End: 2020-11-07 06:00:00 CET, Duration: 6 hours.

Reason: Reconstruction. Due to reconstruction work carried out by the local authorities. Relined is obliged to relocate a section of her network. This activity will impact the following dark fiber circuits: SDC1, Dronten < – > SDC2, Meppel

Expected Outage: Is expected downtime of DWDM channels from the SDC1, Dronten to the SDC2, Meppel only. None expected outage for IP transit service, other dark fibers will automatically take over the data traffic, but there is a small chance for high latency and short time packet loss in the time of rebuild routing tables.