dinsdag 6th juli 2021

Serverius: Planned maintenance of one of the Core routers at DC1, gepland 2 jaar geleden

Onderstaand bericht ontvingen wij van Serverius:

You’re receiving this message as an advanced notice because we are going to do some maintenance that will impact the service that we as Serverius provide to you:

Location = DC1, Dronten Service Type = IP transit.

Start: 2021-07-27 04:00:00 CEST End: 2021-07-27 06:00:00 CEST Duration of outage: 01:00 Reason: Software upgrade of the first Core router.

We will carry out maintenance that will improve our datacenter network.

Expected Outage: No expected outage of the IP transit service for customers who have a redundancy connection or connections to other routers. Other routers will automatically take over the data traffic.

We apologize in advance for the inconvenience that this might cause.